IMAGE - Info-Travaux
Info-works

Cars and (non-oversized) standard trucks can now borrow a smaller detour to cross downtown Saint-Lazare

Replacement of a storm sewer pipe on Chemin Sainte-Angélique

*Oversized trucks should take of the two longer detours  in place for safety reasons.

SAINT-LAZARE (Québec), Thursday, December 14, 2017 - The Town of Saint-Lazare wishes to inform car drivers and drivers of standard (non-oversized) trucks (i.e. trucks that are not oversized like semi-trailers 53 feet long) that they can now use the smaller downtown detour using Rue Denis and Rue des Cèdres to get across both sides of Chemin Sainte-Angélique.


As for oversized trucks, they must continue to use one of the 2 longer detours because of tight intersections at the angle of Rue des Cèdres/Chemin Sainte-Angélique et rue Denis / chemin Sainte-Angélique) and to reduce dangerous manoeuvres in the Auclair school zone. 

For these safety reasons and for the intersection challenges, the LONG detour directional signs will remain in effect.

 

Local deliveries

Businesses are once again invited to inform their suppliers of these instructions.

School boards

School boards have been advised to adjust school bus transportation.

One CIT La Presqu’île bus stop remains suspended

The Sainte-Angélique /rue Leroux remains suspended until the complete reopening of Chemin Sainte-Angélique on December 22. Public transit users will be invited to wait for the bus at the corner of Rue des Cèdres (p.m.) /rue Daniel (a.m.) or Rue des Marguerites (a.m. and p.m.). Bus # 51 will use the detour via Rue Denis and Rue des Cèdres to get back onto Chemin Sainte-Angélique during the major obstruction period.


Emergency services

Emergency services, including ambulances have been advised.


Question / preoccupations

The Town apologises for the inconveniences this work may cause and thanks you in advance for your understanding and collaboration. For any question or preoccupation, do not hesitate to contact the Infrastructure department at 450-424-8000, ext. 235 or 311.

To follow this work: http://www.ville.saint-lazare.qc.ca/en/infotravaux

Replacement of a storm sewer pipe on Chemin Sainte-Angélique


Closure of part of Chemin Sainte-Angélique in downtown Saint-Lazare from Tuesday, December 5 to Friday, December 22, 2017

SAINT-LAZARE (Québec), Friday, December 1, 2017 - The Town of Saint-Lazare wishes to advise motorists, cyclists, business owners, parents as well as public transit users of a major traffic obstruction on Chemin Sainte-Angélique in the downtown core starting at 7 a.m. on Tuesday, December 5, 2017 for a scheduled 9 to 10 days, ending approximately Friday, December 15, 2017 and then of a local traffic obstruction for a another 7 to 8 days, starting Friday, December 15 to Friday, December 22, 2017.

Work area
The work seeks to replace a storm sewer pipe located on Chemin Sainte-Angélique in the area of Rue Daniel and Rue des Cèdres. This work also includes temporary paving work. The permanent paving of the road will be done in the spring of 2018 when the conditions are the most favorable (other closures to be expected in 2018).

Major obstruction from Tuesday, December 5 to Friday, December 15: two (2) major detours depending on which side of downtown needs to be accessed
From Tuesday, December 5 to Friday, December 15, the work planned will require the downtown core to be cut-off in two (2) sectors: the sector « east of Rue Daniel / Rue des Cèdres » and the sector « west of Rue Daniel / Rue des Cèdres ». Motorists, suppliers, and parents will have to follow one of two (2) major detours depending on which side of town they wish to access. Let’s note that at the beginning of the work (approximately from Tuesday, December 5 to Tuesday, December 12) the restaurant La Pataterie La Belle Province will be accessible using the “west” detour of rue Daniel / rue des Cèdres (and then by the “east” detour after that). Motorists should rely on road signs in place for the duration of the detours in effect.
Detour to access the sector « east of Rue Daniel / Rue des Cèdres »
Detour to access the sector « west of Rue Daniel / Rue des Cèdres »

Local obstruction from Friday, December 15 to Friday, December 22: smaller detour by Rue Denis and Rue des Cèdres
Around Friday, December 15 until Friday, December 22, the work will continue, this time, without completely cutting off east to west traffic on Chemin Sainte-Angélique. Motorists will have to use a smaller detour to get from one side of Chemin Sainte-Angélique to the other. Motorists are once again invited to rely on road signs in place for the duration of the detours.



Local deliveries and access to businesses
Businesses remain accessible. The Town encourages business owners, daycares and schools to inform their suppliers of these important detours should they deliver goods during the work.

School transport, access to schools and daycares
Schools and daycares will be informed and bus transportation adjusted. Parents who usually drive through downtown to drop-off their kids at school or daycare should plan to leave earlier and take these delays into account. Always rely on road signs in force.

Three (3) bus stops (CIT La Presqu’île) suspended / delays to be expected
From Tuesday, December 5 to Friday, December 22, three (3) bus stops will be suspended: Sainte-Angélique/des Marguerites, Sainte-Angélique /rue Leroux and Sainte-Angélique/rue Daniel. Public transit users will be invited to wait for the bus at the corner of Sainte-Angélique / Avenue Bédard or Sainte-Angélique / Rue Brazeau. They should also expect delays (and to miss their bus connections) or plan to leave earlier. Bus # 51 will use the detour via Avenue Bédard, Chemin Saint-Louis and Chemin Chevrier to get back onto Chemin Sainte-Angélique during the major obstruction period. From Friday, December 15 to Friday, December 22, it is possible only one bus stop be suspended (Sainte-Angélique/Leroux). The information will be confirmed by the CIT (http://www.citlapresquile.qc.ca).


Parking for residents / businesses on rue Daniel and rue des Cèdres
Parking remains accessible for residents, as well as visitors and customers.

Preventative boil advisory
Only those home owners, whose water entry require modification, will be invited to boil their water as a precautionary measure. They will be informed individually when the time comes.
Detour by Rue Denis and Rue des Cèdres to get across town

Emergency services
Emergency services, including ambulances have been advised.

Question / preoccupations
The Town apologises for the inconveniences this work may cause and thanks you in advance for your understanding and collaboration. For any question or preoccupation, do not hesitate to contact the Infrastructure department at 450-424-8000, ext. 235 or dial 3-1-1.

To follow this work: http://www.ville.saint-lazare.qc.ca/en/infotravaux

 

Ongoing paving (resurfacing) work


Wednesday, November 15, 2017

- part of Rue Thorncliff from Rue Brentwood Street to Rue Nest on ± 60 metres;

-Croissant Montrose;

- Croissant Rosedale. This addition was considered to be adjacent toRue Thorncliff;

- Rue Boisoleil;

- Rue Normandeaut, from Chemin Sainte-Elisabeth until quantity remains.

Work on the Sainte-Angélique aqueduct network

Major traffic obstruction downtown Saint-Lazare on Tuesday, November 14, 2017

SAINT-LAZARE (Québec), Friday, November 10, 2017 - The Town of Saint-Lazare wishes to advise motorists and cyclists of a major traffic obstruction on Chemin Sainte-Angélique in the downtown core starting at 4 a.m. on Tuesday, November 14, 2017 for a scheduled 8 hours-work. Despite the detour signs, businesses will remain accessible.

The work seeks to repair a water main break. This work will be following by paving work if the weather conditions are favorable. Should this not be the case, Chemin Sainte-Angélique will be reopened to traffic and paving will be done subsequently. At that time, traffic will be directed one lane at a time.

Owners of properties aimed by the preventative boil water advisory have already been informed.

The Town apologises for the inconveniences this work may cause and thanks you in advance for your understanding and collaboration.

To follow this work:  http://www.ville.saint-lazare.qc.ca/en/infotravaux  


Work on the Sainte-Angélique aqueduct network and sewers

Major traffic obstruction downtown Saint-Lazare on November 6 and 7, 2017

*Paving work on Thursday, November 9, 2017, from 9 a.m. to 4 p.m.


SAINT-LAZARE (Québec), le jeudi 2 novembre 2017 - The Town of Saint-Lazare wishes to advise motorists and cyclists of a major traffic obstruction on Chemin Sainte-Angélique in the downtown core starting 8:30 a.m. on Monday, November 6, 2017 for a scheduled 2 days-work. The work will be followed by paving, on Thursday November 9, 2017, between 9 a.m. and 4 p.m. Despite the detour signs, businesses will remain accessible to local traffic..

The work on the aqueduct and sewer networks seeks to service an upcoming multiple family-dwelling project. This work will be following by the paving work if the weather conditions are favorable. Should this not be the case, Chemin Sainte-Angélique will be reopened to traffic and paving will be done subsequently. At that time, traffic will be directed one lane at a time.

Owners of properties aimed by the preventative boil water advisory have already been informed.

The Town apologises for the inconveniences this work may cause and thanks you in advance for your understanding and collaboration.

To follow this work: ville.saint-lazare.qc.ca/en/infotravaux

Major traffic obstruction downtown Saint-Lazare on November 6 and 7, 2017

Closure of Chemin Saint-Louis for CP work


Tuesday, October 31, November 1 and 2, 2017

The road will partially be closed, in the Chaline Valley, on October 31st, November 1st and 2nd, 2017 from 8:30 am to 5:00 pm.

Detour via the rue du Carillon.

Parc Westwood and Parc Saint-Robert in Saint-Lazare

Tree cutting and paving of parking lots

SAINT-LAZARE (Quebec), on Friday, October 6th, 2017 – Ville de Saint-Lazare wishes to inform residents that it will proceed, starting in the week of October 9th, 2017, with the work required to improve park user safety and access to emergency vehicles, including those of first responders, as well as improve access to handicapped people and people with reduced mobility in Parc Westwood and Parc Saint-Robert. In both cases, water gardens will be made to recover rain waters, an ecological solution which allows water to be retained and filtered through vegetation which naturally eliminates pollutants!  The work should be completed by the end of this year if weather conditions are favorable.

Parc Westwood

The work planned in Parc Westwood will allow doubling the surface of the car park; increasing parking spaces form 50 to 100. This will reduce the number of cars parked on the streets and leave more room for emergency vehicles should they need to come through.  This expansion, however, will require tree cutting in two areas. The existing car park will remain open until the expansion is completed. The whole car park will be temporarily closed at the time of the paving. Once completed, the car park will be accessed from chemin Saint-Louis as well as Rue des Sportifs.


Parc Saint-Robert

The work planned in Parc Saint-Robert, on the other hand, consists of paving the main entrance to improve access to handicapped people and people living with a reduced mobility. A drop-off zone will also be paved alongside the sports fields.

The Town apologizes for any inconvenience this work may cause and thanks you in advance for your collaboration and for your understanding.

To follow this file: http://www.ville.saint-lazare.qc.ca/en/infotravaux.

Chemin Sainte-Angélique


Thursday, September 7th, 2017
Road Work on chemin Sainte-Angelique
Detour by Rue Albert-Beaulne

Chemin Sainte-Angelique will be closed to traffic between Rue Gosselin and Rue Grand Pré. A detour has been created via Rue Albert-Beaulne.

Thank you for your patience!

Pavement work


There will be construction works on August 17 on the following streets :

  • Rue Maple Ridge;
  • Rue Campbrigde;
  • Croissant Chaline;
  • Place Cardin;
  • Place Surrey.

Maintenance Work


Update: July 27, 2017

Maintenance Work –Trans Canada’s natural gas pipeline

Direction(s)

In both directions

Location

Cité des Jeunes Boulevard (Highway 340), close to rue des Monarques.

Nature of the work

Maintenance work

Calendar

July 28, 2017, to August 31, 2017.

Obstruction(s)

Complete closure of Route 340 (Cité-des-Jeunes), in both directions, near rue du Parc Industriel;

Traffic will be directed on the deviation road constructed by Trans Canada Pipeline.


Questions

514-982-8420




Street works

No street works
Ville de Saint-Lazare © 2002-2017
1960, chemin Sainte-Angélique, Saint-Lazare (Québec), J7T 3A3
Telephone: 450 424-8000

The Town ·  Municipal services ·  Things to do ·  History, maps & statistics ·  Environment ·  Transportation & public works ·  Public safety  ·   Contact us